Elk Ridge City
Water | Water Distribution System Improvements
|
|
Several residential service laterals, fire hydrants and valves were also replaced as part of the project. The pipelines were installed parallel to existing line so that service could be maintained to customers with minimal disruptions. Testing, flushing and disinfection were completed prior to taking the old lines out of service and making the connections to the new line. Asphalt roadway patching and re-vegetation of disturbed areas were also included.
|
Project Summary:
Client |
Elk Ridge City |
Reference |
*Available upon request |
Location |
Elk Ridge, UT |
Cost |
$20,000 |
Features |
|